The following is an outline of the basic project plans from 2007-2009. Details of these upgrades can be found on teh Utilities Kingston website.
LONG TERM PLANS
2007
Start construction of new Biosolids Storage building
Start-up Co-Gen
Excavate for new Digester
2008
Begin mechanical work for BAF
Start first BAF cells (late in year)
Start building new Digester
Start-up new Dewatering equipment
Start using new Biosolids Storage
2009
Complete start-up of all equipment
Start testing BAF performance
Complete landscaping and restoration
Ribbon Cutting and Open House